New HVAC units.
|
|
Drywalling and mud work almost complete for the operations hall.
|
|
Maintenance access stairs.
|
|
Walking the generator with the help of the crane to the back of the building.
|
|
Another shot of the generator installation.
|
|
Turning the corner with the generator.
|
|
Opps, we had to turn the generator around.
|
|
Concrete pad for the generator.
|
|
Home sweet home for the generator (dubbed "Big Alice").
|
|
A scenic view from inside the steel framing of the tower.
|
|
A view of our neighbors across from the TMC.
|
|
Installation of one heavy duty roof.
|
|
Scaffolding going up around tower.
|
|
A view of the rear of the TMC - including the newly installed generator.
|
|
View of the front entry and tower construction.
|
|
Applying the corner molding to the polished block corridor.
|
|
View of the lobby looking out the front entrance.
|
|
Landscaping the hillside behind the TMC.
|
|
The hillside is seeded and ready for rain.
|